On September 11, the Lake Forest Park City Council approved Resolution 25-2028 allowing the City to move forward with a contract with Johansen
Construction Company for the SR 104 and 40th Place NE Roundabout
project.
After a competitive bidding process in July, Johansen Construction Company was selected with the lowest responsible bid of $5.4 million. The total project cost is estimated at $8.6 million.
Construction is scheduled to begin in late spring 2026 and is expected to last approximately 18 months. Once complete, the roundabout will improve traffic flow and safety for drivers, pedestrians, and cyclists and will feature new sidewalks, shared-use pathways, pedestrian crossings with refuge islands, and upgraded street lighting.
More information, including contract details, are available in the City Council meeting minutes. You can also learn more about the project on the City’s website.
Questions? For more information, please contact:
Mike Read
Senior Project Manager
(206) 957-2836 | mread@cityoflfp.gov
Katie Phillips
Project Manager
(206) 957-2812 | kphillips@cityoflfp.gov
Smoky haze, with a high of 85 and low of 54 degrees. Smoky haze in the morning, clear overnight.
After I completed the very first Community Police Academy (I would highly recommend participating in this), I had the honor of doing my "ride along" with Sgt Walker. A true compassionate professional and an asset to our LFP police department.
What an excellent choice. Chief Zanella will do an excellent job leading our LFP PD.